Development and maintenance
AGL undertook a wide range of comprehensive studies to determine the impact of Oaklands Hill Wind Farm on ecology, landscape, cultural heritage, visual amenity and other environmental factors. Following a robust development process, a planning permit was issued in late 2008.
AGL commenced construction of Oaklands Wind Farm in mid-2010, with practical completion achieved in February 2012.
Suzlon Energy Australia Pty Ltd (SEA) was awarded the Engineer Procure & Construct (EPC) contract – they installed 32 Suzlon S88 turbines with a capacity of 2.1 MW each. The total output from the wind farm is capped at 63 MW. Suzlon are also responsible for the ongoing maintenance of the site.