The next community consultative meeting for the Silverton Wind Farm will be held on Tuesday, 19 September 2017 between 3-5pm at the Silverton Municipal Chambers.

AGL encourages those interested to come along and hear firsthand how their local contractors and suppliers are helping to shape the wind farm.

Construction of the Silverton Wind Farm is progressing to plan. The number of construction personnel has also grown to approximately 80 during August as the structural works commenced.

AGL’s Silverton Wind Farm Project Manager, Adam Mackett, acknowledged the efforts of the EPC contractor, GE- CATCON and their local subcontractor, Mawsons Concrete & Quarries on the successful first concrete pour which has been delivered on time.

The 200MW Silverton Wind Farm is the first greenfield development for the Powering Australian Renewables Fund (PARF) and will be the largest in NSW when complete in mid-2018 and will provide approximately 780,000 MWh of renewable energy annually, which equates to the power supply of approximately 137,000 average Australian homes.

Below are images from the construction phase.

170825B 1137hrs_WTG11 concrete pour

170825D 1137hrs_WTG11 concrete pour

About AGL
AGL is committed to helping shape a sustainable energy future for Australia. We operate the country’s largest electricity generation portfolio, we’re its largest ASX-listed investor in renewable energy, and we have more than 3.6 million customer accounts. Proudly Australian, with more than 180 years of experience, we have a responsibility to provide sustainable, secure and affordable energy for our customers. Our aim is to prosper in a carbon-constrained world and build customer advocacy as our industry transforms. That’s why we have committed to exiting our coal-fired generation by 2050 and why we will continue to develop innovative solutions for our customers.